Metro Plaza Mixed-Use
Project Details
Metro Plaza Mixed-Use
Complete project details and information
Project Information
Project Name
Metro Plaza Mixed-Use
Project Type
Turnkey ProjectCreated Date
3/15/2025
Current Phase
Foundation
Progress
6 of 11 phases completed
Status
ActivePhase Timeline
1
Concept Design
2025-04-01 to 2025-05-15
2
Schematic Design
2025-05-20 to 2025-07-30
3
Design Development
2025-08-05 to 2025-10-15
4
Construction Documents
2025-10-20 to 2025-12-20
5
Permits & Approvals
2025-12-22 to 2026-01-03
6
Procurement
2026-01-02 to 2026-01-04
7
Foundation
2026-01-05 to 2026-03-20
8
Structure
2026-03-21 to 2026-07-31
9
MEP Installation
2026-05-15 to 2026-09-30
10
Finishing
2026-08-01 to 2027-01-15
11
Handover
2027-01-20 to 2027-02-28