Metro Plaza Mixed-Use

Project Details

Metro Plaza Mixed-Use

Complete project details and information

Project Information

Project Name

Metro Plaza Mixed-Use

Project Type

Turnkey Project

Created Date

3/15/2025

Current Phase

Foundation

Progress

6 of 11 phases completed

Status

Active
Phase Timeline
1

Concept Design

2025-04-01 to 2025-05-15

2

Schematic Design

2025-05-20 to 2025-07-30

3

Design Development

2025-08-05 to 2025-10-15

4

Construction Documents

2025-10-20 to 2025-12-20

5

Permits & Approvals

2025-12-22 to 2026-01-03

6

Procurement

2026-01-02 to 2026-01-04

7

Foundation

2026-01-05 to 2026-03-20

8

Structure

2026-03-21 to 2026-07-31

9

MEP Installation

2026-05-15 to 2026-09-30

10

Finishing

2026-08-01 to 2027-01-15

11

Handover

2027-01-20 to 2027-02-28