Riverside Corporate Tower

Project Details

Riverside Corporate Tower

Complete project details and information

Project Information

Project Name

Riverside Corporate Tower

Project Type

Turnkey Project

Created Date

1/22/2026

Current Phase

Schematic Design

Progress

1 of 11 phases completed

Status

Active
Phase Timeline
1

Concept Design

2025-09-01 to 2025-10-15

2

Schematic Design

2025-10-20 to 2025-12-15

3

Design Development

2025-12-20 to 2026-03-01

4

Construction Documents

2026-03-05 to 2026-07-15

5

Permits & Approvals

2026-07-20 to 2026-10-01

6

Procurement

2026-10-05 to 2026-11-15

7

Foundation

2026-11-20 to 2027-02-28

8

Structure

2027-03-01 to 2027-08-31

9

MEP Installation

2027-06-01 to 2027-11-30

10

Finishing

2027-10-01 to 2028-03-31

11

Handover

2028-04-01 to 2028-05-15