Riverside Corporate Tower
Project Details
Riverside Corporate Tower
Complete project details and information
Project Information
Project Name
Riverside Corporate Tower
Project Type
Turnkey ProjectCreated Date
1/22/2026
Current Phase
Schematic Design
Progress
1 of 11 phases completed
Status
ActivePhase Timeline
1
Concept Design
2025-09-01 to 2025-10-15
2
Schematic Design
2025-10-20 to 2025-12-15
3
Design Development
2025-12-20 to 2026-03-01
4
Construction Documents
2026-03-05 to 2026-07-15
5
Permits & Approvals
2026-07-20 to 2026-10-01
6
Procurement
2026-10-05 to 2026-11-15
7
Foundation
2026-11-20 to 2027-02-28
8
Structure
2027-03-01 to 2027-08-31
9
MEP Installation
2027-06-01 to 2027-11-30
10
Finishing
2027-10-01 to 2028-03-31
11
Handover
2028-04-01 to 2028-05-15